A vehicle being carried by a tow truck down a flooded road in Pinewood Gardens community after heavy rains flooded the area over the weekend. Photo: Nikia Charlton
By JADE RUSSELL
Tribune Staff Reporter
jrussell@tribunemedia.net
WORK on Pinewood's $2.6m pilot drainage system is due to begin today with two lift stations, days after floodwaters trapped residents in their homes and submerged their cars.
Many residents spent days hauling water-damaged furniture and belongings out of their homes after last week's heavy rain, and the latest flooding has left the community at the end of its patience. Several residents told The Tribune they wanted a lasting solution from the government, not more promises.
Pinewood MP Myles Laroda told reporters on Friday that work on the project would initially involve two lift stations. He acknowledged that his constituency had flooded badly, but pushed back against the perception that Pinewood was the only community severely affected, saying several other parts of New Providence had faced similar conditions.
The Ministry of Works sent pump trucks to help drain flooded areas across the island last week.
Mr Laroda also pointed to an $80m loan from the Inter-American Development Bank (IDB) for climate resilience and flood mitigation, which the bank approved last December. Parliament is expected to debate a resolution to borrow the money in the coming weeks, with $17m earmarked for flood remediation in Pinewood.
The pilot project's scope has shifted since the government announced it in July. It was first described as four lift stations: at Sapodilla Street; Bay Geranium Avenue; Pigeon Plum Street, between Saffron and Croton streets; and Jones Heights, off East Street South.
A week later, during a visit to the community, Works Minister Clay Sweeting spoke of three stations, at Sapodilla Boulevard, Pigeon Plum Street and Jones Heights. It remains unclear whether the plan was revised or whether Bay Geranium Avenue is still included.
When the project was announced in July, Mr Sweeting said the equipment was being manufactured and was expected to arrive within three to four weeks. The work was expected to take about 12 months once construction began.
The lift stations are designed to switch on automatically when water in designated catchment areas reaches a set level, pumping the excess into specially built deep disposal wells when heavy rain overwhelms the area's natural drainage. Mr Sweeting compared them to the bilge pumps on a boat.
Officials have said the system should reduce standing water and improve drainage without relying solely on traditional gravity drainage or on trucks to remove floodwater.
Pinewood has flooded for decades, and during Tropical Storm Imelda some residents were trapped for days or had to be rescued. Mr Sweeting said in July that the pilot could shape how the government tackles flooding elsewhere in New Providence, and a similar system has been proposed for Coral Harbour.